Alrewas

The scope of the project was to supply and install a new sand washing plant with integral two stage de-ligniting to replace the existing sand plant at the Alrewas Site, located near Burton-on-Trent.

The process was designed to handle up to 250 t/h of sand and 260 m3/hr of water that will produce a single decontaminated "concreting" sand product. 

The new plant was delivered, erected and commissioned between November 2006 and May 2007.